The Minister of transportation, Rotimi Amaechi, , on Tuesday in Ibadan, said the ongoing Standard Gauge Railway from Abeokuta to Ibadan was 70 to 80 per cent completed.
The News Agency of Nigeria (NAN) reports that the minister had alongside Gov. Abiola Ajimobi of Oyo State and many others, drove round the project to the end in Ibadan axis.
“Let me tell you that this project is 70 to 80 percent completed. We are in Ibadan already with the track and hopefully, before the end of the year, commercial activities should start on the track.
“We are trying to go to Ibadan through the route. We have travelled 136km and what is remaining is about 22km, so we are almost through to the end.
“Actually it is 156km and we have exactly 2km to Ibadan Inland Dry Port, so it is 158km. If we have done 136km, then what is remaining is just 22km,’’ Amaechi said.
The minister said the expectation was that work should be at its last lap by the end of May or second week of June if the contractors work on four kilometres per day.
Amaechi said that the contract was just two years and they had gone this far, saying that it was a pointer to the fact that the present government was committed to the completion of the project.
“President Muhammadu Buhari is focusing more on infrastructure. I listened to the radio on Monday and Nigeria is rated among the first 10 countries in Africa growing in infrastructure.
“We believe that if the president continues what he is doing and such is consolidated by another government, then we can be up there,’’ he said.
The minister thanked all the communities on the Lagos-Ibadan railway track, saying that they never experienced any form of confrontation from them since the project started.
“I wish to thank all the communities on the railway track from Lagos. They have been very cooperative. Even when schools were demolished on the route, they gave us time to rebuild them,’’ he said.
Ajimobi told newsmen that he was happy with the speed at which the contractors were working on the project, saying the completion of the project would astronomically lift socio-economic development.
He commended the Buhari-led government for investing on infrastructure like his administration did in Oyo, saying such effort would soon bring about the much-desired society.
Among those in the entourage were members of the State Executive Council, officials of Federal Ministry of Transportation as well as Nigerian Shippers’ Council.
NAN reports that work is ongoing on the project as railway tracks have been laid on some sections of the Ibadan axis, while construction work is ongoing on others.(NAN)
Abeokuta-Ibadan Standard Gauge Railway Near Completion, Says Amaechi
May 21, 2019
0
Tags
Share to other apps
Thank you for reaching out to us. We are happy to receive your opinion and request. If you need advert or sponsored post, We’re excited you’re considering advertising or sponsoring a post on our blog. Your support is what keeps us going. With the current trend, it’s very obvious content marketing is the way to go. Banner advertising and trying to get customers through Google Adwords may get you customers but it has been proven beyond doubt that Content Marketing has more lasting benefits.
We offer majorly two types of advertising:
1. Sponsored Posts: If you are really interested in publishing a sponsored post or a press release, video content, advertorial or any other kind of sponsored post, then you are at the right place.
WHAT KIND OF SPONSORED POSTS DO WE ACCEPT?
Generally, a sponsored post can be any of the following:
Press release
Advertorial
Video content
Article
Interview
This kind of post is usually written to promote you or your business. However, we do prefer posts that naturally flow with the site’s general content. This means we can also promote artists, songs, cosmetic products and things that you love of all products or services.
DURATION & BONUSES
Every sponsored article will remain live on the site as long as this website exists. The duration is indefinite! Again, we will share your post on our social media channels and our email subscribers too will get to read your article. You’re exposing your article to our: Twitter followers, Facebook fans and other social networks.
We will also try as much as possible to optimize your post for search engines as well.
Submission of Materials : Sponsored post should be well written in English language and all materials must be delivered via electronic medium. All sponsored posts must be delivered via electronic version, either on disk or e-mail on Microsoft Word unless otherwise noted.
PRICING
The price largely depends on if you’re writing the content or we’re to do that. But if your are writing the content, it is $60 per article.
2. Banner Advertising: We also offer banner advertising in various sizes and of course, our prices are flexible. you may choose to for the weekly rate or simply buy your desired number of impressions.
Technical Details And Pricing
Banner Size 300 X 250 pixels : Appears on the home page and below all pages on the site.
Banner Size 728 X 90 pixels: Appears on the top right Corner of the homepage and all pages on the site.
Large rectangle Banner Size (336x280) : Appears on the home page and below all pages on the site.
Small square (200x200) : Appears on the right side of the home page and all pages on the site.
Half page (300x600) : Appears on the right side of the home page and all pages on the site.
Portrait (300x1050) : Appears on the right side of the home page and all pages on the site.
Billboard (970x250) : Appears on the home page.
Submission of Materials : Banner ads can be in jpeg, jpg and gif format. All materials must be deliverd via electronic medium. All ads must be delivered via electronic version, either on disk or e-mail in the ordered pixel dimensions unless otherwise noted.
For advertising offers, send an email with your name,company, website, country and advert or sponsored post you want to appear on our website to advert @ alexa. ng
Normally, we should respond within 48 hours.